Unique Design B.V. - Generator load test – Maintenance details

Generator load test

Completed
Scheduled for 03 September 2026 at 7:00 AM – 8:00 AMUTC

Affects

Eurofiber Cloud Infra - Waalwijk, NL

Under maintenance from 7:00 AM to 8:00 AM

Eurofiber Cloud Infra power network

Under maintenance from 7:00 AM to 8:00 AM

Updates
  • Update
    03 September 2026 at 8:00 AMUTC
    Update
    03 September 2026 at 8:00 AMUTC
    Maintenance has completed successfully
  • Completed
    03 September 2026 at 8:00 AMUTC
    Completed
    03 September 2026 at 8:00 AMUTC
    Maintenance has completed successfully
  • Update
    03 September 2026 at 7:00 AMUTC
    Update
    03 September 2026 at 7:00 AMUTC
    Maintenance is now in progress
  • In progress
    03 September 2026 at 7:00 AMUTC
    In progress
    03 September 2026 at 7:00 AMUTC
    Maintenance is now in progress
  • Planned
    03 September 2026 at 7:00 AMUTC
    Planned
    03 September 2026 at 7:00 AMUTC

    During this test, the generator sets will start and take over the data center's power supply, running parallel to the public grid. The generators will handle the full load while the public power remains available. There's a small risk of a brief power interruption during switching, but the UPS systems will cover any short interruptions, ensuring no impact on your rack.