Unique Design B.V. - Extensive generator load test – Maintenance details

Extensive generator load test

Planned
Scheduled for 08 April 2026 at 2:00 PM – 3:00 PM

Affects

Eurofiber Cloud Infra - Waalwijk, NL

Under maintenance from 2:00 PM to 12:00 AM

Eurofiber Cloud Infra power network

Under maintenance from 2:00 PM to 12:00 AM

Updates
  • Planned
    08 April 2026 at 2:00 PM
    Planned
    08 April 2026 at 2:00 PM

    During this test, the generator sets will start and take over the data center's power supply, running parallel to the public grid. The generators will handle the full load while the public power remains available. There's a small risk of a brief power interruption during switching, but the UPS systems will cover any short interruptions, ensuring no impact on your rack.