Unique Design B.V. - Power System Maintenance – Maintenance details

Power System Maintenance

Completed
Scheduled for 03 February 2025 at 6:00 AM – 2:16 PM

Affects

Eurofiber Cloud Infra - Waalwijk, NL

Under maintenance from 6:00 AM to 2:16 PM

Eurofiber Cloud Infra power network

Under maintenance from 6:00 AM to 2:16 PM

Updates
  • Completed
    03 February 2025 at 2:16 PM
    Completed
    03 February 2025 at 2:16 PM

    The scheduled UPS firmware update at the Waalwijk DC on February 3, 2025, has been successfully completed. The Technical Ops Team wishes you a great week ahead!

  • In progress
    03 February 2025 at 6:00 AM
    In progress
    03 February 2025 at 6:00 AM
    Maintenance is now in progress
  • Planned
    03 February 2025 at 6:00 AM
    Planned
    03 February 2025 at 6:00 AM

    On February 3, 2025, our partner Eurofiber Cloud Infra will perform scheduled firmware updates on the UPS (Uninterruptible power supply) installation in Data Room 1, Waalwijk. The maintenance will take place between 7:00 and 17:00 CEST. While no disruptions are expected, there is a minimal risk of impact on the A-feed and B-feed availability.